Demolition Permit Requirements
A demolition permit is required prior to the demolition of
any structure within the city limits. The following conditions apply to
demolition permits:
- A site plan is required showing all structures on the
property. Highlight or otherwise indicate the structures(s) to be removed.
- A floor plan, or sketch, of the structure(s) is required
showing the room designation and plumbing fixtures.
- The applicant must complete a Building Permit
Application along with the Demolition Information Sheet.
- Hazardous materials (including asbestos) must be removed
and disposed of properly. DEP notification is required if excessive amounts of
asbestos are removed.
- Demolition materials must be removed from the site and
disposed of at a landfill and/or recycling facility.
- A demolition permit is valid for 30 days. A 30 day
extension may be granted by the building official for cause.
- An Owner/Contractor Disclosure Statement must be signed
by an owner/occupant of a residential building acting as their own asbestos
abatement contractor.